Development of Medan-Binjai toll road in North Sumatra province gained traction with payment of land compensation in two sections on August 12. Physical construction of Section III of the toll road has been completed 60.54% by August 19, while Section II has reached 43%. A month ago, physical contruction of Section III and II reached 52.8% and 36% respectively. Accordingly, we can expect commercial operation of this toll road next year.To subscribe please click here